Iron Gate II |
Designer: | The Design Institute for Road, Water and Air Transport, Bucharest | ||
Main contractor: | The Enterprise for Hydrotechnical Constructions "Iron Gate II" | ||
Owner of the bridge: |
Location and name of the bridge: | |||
Name(s) of the bridge: | Bridge over
the Djerdjap II hydro-power and navigation system (Yugoslavian part) |
||
Distance: | 863+000 km | ||
Country: | Yugoslavia-Romania | ||
City/town | Prahovo-Negotin | ||
Route: | M-25 transition Yu-Ro | ||
Year of building - completion: | 1985., partly in construction |
Span lengths: | max. 40 m, others: 29.8-38 m 16 spans finished, 16 ones under constr. |
||
Roadway widths: | 7.5 m, total width: 10.45 m | ||
Designer: | IPTANA-Bucharest | ||
Main contractor: | Energoprojekt-Izgradnja, Beograd | ||
Owner of the bridge: | Hydropower Plant Djerdap |